Completion and Commissioning of FYIP-CPF/CCP Plant & North Bank Flow Station.

Addendum to Section IV (B) Scope of Work (FYIP New Onshore Scope - Phase II)

 

SCOPE OF WORK:

The work scope entails completion of outstanding work items before contractor was temporarily demobilized from site, remedial works as a result of the site abandonment, punchlist items from inspections, punchlist items from pre-startup audits, any other identified work items, and commissioning of the facilities. In summary, the work scope is to complete all works necessary and incidental to the completion, commissioning and handover of the facilities to Operations.
 

 

The new onshore EPC scope is primarily the upgrade of the North Bank and Yokri Flow Stations and green field additions to CPF gas processing facilities.  The main objectives of this scope among others are to achieve: Compression of Gas for process purposes, sales of export gas to Nigerian Domestic Gas market and reduction of flaring by recovery of associated gas. 
It will involve the design, procurement, installation and commissioning of; (i) Two screw compressors, (ii) Two reciprocating compressors, (iii) One single train JT-LTS unit, and (iv) NAG Slug Catcher. 
Design has progressed significantly while procurement of the long lead items has been placed.
This new phase is running concurrently with the completion of the existing facilities.
 

CLIENT

SPDC

Site

FORCADOS YOKRI – Delta State

Project Description

FYIP Work CCP/CPF & North Bank Flow Station

Scope of Work

Forcados –Yokri Integrated Project Contract – Onshore EPIC Works CCP/CPF and North Bank Flow Station Plus Addendum to Section IV (B) Scope of Work (FYIP-New Onshore Scope (Phase II) Variation)

Actual Progress

 44.36%

 

Total Amount (USD)

 $212,000,000.00

 

Project News

Alcon succesfully completed the HAZOP and SIL workshop for the procurement and installation of two numbers export compressors supplied by ENERFLEX